Tunnel Boring Trial, Northparkes Mines, NSW, Australia

THE PROJECT

As part of its Mine of the Future program, Rio Tinto began a trial of a prototype tunnel-boring machine in 2013 at its Northparkes underground copper-gold mine. The goal of the project was to demonstrate that mechanised means of excavation can be faster than conventional drill-and-blast methods when establishing new-block cave mines. The tunnel-boring machine was to excavate a 1.4 km long horizontal drive at a depth of 600 m in hard rock. Ground support comprised rock bolts and shotcrete, installed by the machine.

PSM was engaged to provide site geotechnical support to the tunnel-boring team. PSM was also responsible for preparing factual and interpretive site investigation reports and a ground control management plan (GCMP) for the development drive.

ENGINEERING AND TECHNICAL OPPORTUNITIES

A novel excavation method in combination with high in-situ stresses and jointed volcanic lithology led to challenging rock mass behaviour. Unexpected operational problems as a result of use of a prototype machine needed timely geotechnical solutions. Underground geotechnical support was required at all times during the 24-hours a day excavation. The trial nature of the project was an opportunity to collect extensive data collection and monitor the program to assess machine performance and rock mass behaviour.

APPROACH AND INNOVATION

Following rigorous assessment and modelling, PSM’s tailored approach included:

  • Investigation of up to 800 m long horizontal cored boreholes parallel to the drive
  • Implementation of a geotechnical and seismic monitoring program comprised of geophones, accelerometers, rod and wire extensometers, and hollow inclusion stress cells
  • Collection of data using LiDAR scanning to assess shotcrete thickness, crack-pin monitoring of spalling ground, Schmidt hammer testing for rock strength and photographic assessment of muck size
  • Development of a risk assessment system to allow access to the excavation face.

OUTCOMES

PSM provided geotechnical support which could be adapted to the dynamic process of a trial operation, while still maintaining a strong technical basis. The successful large monitoring and instrumentation program incorporated innovative data collection methods leading to improved data quality, safety to personnel and saved time.

Services: #Geotechnical #Northparkes #Tunnelling

get in touch

Contact Us

For expert advice, reach out to our team today.

    SUBSCRIBE TO STAY IN TOUCH

    Receive the latest news and updates straight to your inbox.
    footer certificationfooter certificationfooter certification
    Technically Assured Organisation
    Locations

    Sydney

    G3, 56 Delhi Road
    North Ryde NSW 2113

    BRISBANE

    Level 6, 500 Queen st
    Brisbane QLD 4000

    PERTH

    Level 3, 22 Delhi st
    West Perth WA 6005

    GEELONG

    O16, L4, 60 Moorabool St
    Geelong VIC 3220
    Contact us
    Locations

    Sydney

    G3, 56 Delhi Road
    North Ryde NSW 2113

    BRISBANE

    Level 6, 500 Queen St
    Brisbane QLD 4000

    PERTH

    Level 3, 22 Delhi St
    West Perth WA 6005

    Geelong

    O16, L4, 60 Moorabool St
    Geelong VIC 3220
    Contact us
    Footer Certification
    Footer AEC logo